Do the two things that keep post-mortem action items from dying: convert each accepted
action into a tracked ticket at PIR time, and audit the set on a cadence until every item
is done, deliberately dropped, or escalated — never just forgotten.
CONVERSION (at PIR time):
1. Pull the action items from the post-mortem document or ticket. Only convert items a
human accepted at the review — don't promote every "we could..." musing into committed
work.
2. For each accepted item, require three fields before it becomes a ticket: a SPECIFIC
VERIFIABLE ACTION ("add disk-space alerting on the database volume at 80%," not
"improve monitoring"), an OWNER (a named person — "the infrastructure team" is where
actions go to die; check the team directory to disambiguate), and a DUE DATE proportionate to the
risk it mitigates. Items missing any field go back to the requester as "not trackable
yet: needs <field>" — recorded as such, not silently dropped and not created hollow.
3. Create one ticket per action (on the internal-work board): title "PIR ACTION: <verb phrase> [<incident ref>]", body carrying the
action, incident and post-mortem references, why it matters, owner, due date.
4. Cross-link: a plain-text note on the incident master ticket listing every action ticket
created. If the RFO letter promised specific prevention measures, verify each promise
has a corresponding action ticket and flag any that don't — a written client promise
with no ticket behind it is a liability.
FOLLOW-THROUGH AUDIT (on a cadence, default every 2 weeks until the set closes):
5. search for open PIR-action tickets; classify each from evidence: DONE (closed
with completion evidence — change-completion-verification standard where it was a
change; a bare "done" is unverified), ON TRACK, AT RISK (due within a week, no
activity), OVERDUE, or STALLED (no activity in 30+ days).
6. For overdue/stalled items, post a plain-text nudge note addressed to the owner, and roll
repeat offenders up to the lead: the audit's product is the uncomfortable list —
"incident <ref> was 6 weeks ago; 3 of 5 prevention actions have had zero activity."
7. If a stalled action is being deliberately dropped, require the drop to be explicit: a
note by the owner or lead stating it's descoped and why. Close the ticket referencing
that decision.
8. Report the audit: per incident, actions done / on track / at risk / overdue /
dropped-with-decision, and the follow-through rate over time.
Guardrails: the agent creates tickets, nudges, and reports — it never marks an action done
without evidence, never picks owners itself, never descopes an item on its own judgment.
One action, one ticket, one owner. Verification standard is real: prevention actions that
were changes get the same evidence bar as any change completion. Actions that were client
promises (RFO) can only be dropped with the lead's explicit sign-off. Result-cap honesty:
if the action-ticket search may be capped, say the audit is partial.